IURC Eminent Domain for LEAP Transmission Lines Clears Despite OUCC Objection

The IURC ruling Wednesday gives Wabash Valley Transmission public utility status and the power to condemn Boone County land for two lines feeding the LEAP district in Lebanon, where Eli Lilly plans manufacturing and Meta plans a data center. The commission found Viridon's capital base makes abandonment unlikely. The Office of Utility Consumer Counselor disagreed and is reviewing what happens to Wabash Valley's co-op members if Viridon exits the project the way American Transmission Company is now asking FERC to force in Wisconsin, where Viridon lost certification on a $350 million project in March. The lines are targeted for 2029. If your expansion in Boone County depends on that date, confirm with your serving utility how your service date is tied to these projects, then ask what happens to your interconnection if the corridor slips a year.

Impact
This order is effectively a regulatory workaround for Viridon: the same Blackstone-backed developer was just stripped of three substations on a $350 million Wisconsin transmission project in March after failing to clear public-utility certification fast enough, and American Transmission Company has since filed a 393-page FERC complaint to void Viridon's remaining Wisconsin award entirely. Indiana just handed Viridon exactly the certified status and condemnation authority Wisconsin withheld, meaning if FERC sides with ATC, capital pressure on this Indiana JV could intensify right as Boone County easement negotiations get sensitive, a contingency the OUCC's exit-risk warning wasn't hypothetical about.
Watch
The OUCC's formal review of the order and any FERC ruling on ATC's complaint against Viridon in the parallel Wisconsin case.
For the huddle

How do I find out if my Boone County expansion timeline depends on the LEAP transmission lines?

Ask your serving utility directly whether your interconnection or service date is tied to the Wabash Valley Transmission corridor, then ask what happens to that date if the project slips past 2029.

From the brief, October 4, 2026

  1. IURC Eminent Domain for LEAP Transmission Lines Clears Despite OUCC Objection
  2. Duke Energy's $103 Billion Capital Plan Targets Data Center Load in Indiana
  3. CAFE Rollback Eases Stellantis Kokomo's Engine Math, Not the Legal Risk
  4. Navistar/International Motors Shuts Springfield, Ohio Truck Plant, 1,400 Laid Off Days Before Trump Rally
  5. Trump Rolls Back Biden-Era Fuel Economy Standards, Names Indiana Among States With New Auto Investment
  6. Trump Threatens Up to 300% Tariffs on Foreign Firms That Don't Build U.S. Factories, Names South Korea

The whole day’s brief →

This story

Related

Manufacturers Energy Grant Program

Free for Boone County manufacturers

Boone County manufacturers receive free, ongoing energy auditing and cost control that reduces their energy bills and keeps them low, month after month. Every line item checked and validated, every opportunity found comes with a step-by-step guide to capture it.

EDCs: sponsor this program and it carries your organization's name For economic developers →