AEP and X-energy Formalize Breed Station Plan Amid a Competing CANDU Bid
AEP and X-energy signed a joint development agreement the same day to evaluate the 960-megawatt, 12-reactor project at Indiana Michigan Power's retired Breed Generating Station. AEP's chairman and CEO, Bill Fehrman, said the Amazon-backed structure covers the full project cost so existing ratepayers aren't exposed to construction risk. Hours later, AtkinsRéalis, the State of Indiana, and Hoosier Energy Rural Electric Cooperative signed a separate memorandum of understanding to study up to eight CANDU reactors, as much as 6 gigawatts, at a different retired fossil site.
Indiana now has two nuclear proposals chasing the same brownfield sites, the same workforce, and the same state attention in a single week. A 2024 University of Michigan coal-to-nuclear study ranked AEP's own Schahfer and AES Petersburg plants as better SMR candidates than Breed, which raises the question of whether proximity to I&M's existing Cook plant experience, rather than site quality, drove the choice. The CANDU option carries its own gap: it runs on a heavy-water supply chain with no U.S. production source, meaning full dependency on Canada, a detail missing from the state's framing of the deal as energy independence. Either way, a 960-megawatt Xe-100 build is really twelve sequential first-of-a-kind construction projects, and Indiana doesn't currently have the specialized reactor-construction workforce either one would require.
- Impact
- Indiana now has two competing nuclear bids chasing the same pool of brownfield coal sites, workforce, and state attention in the same week, and a 2024 University of Michigan coal-to-nuclear study ranked AEP's own R.M. Schahfer and AES Petersburg plants as better SMR brownfield candidates than Breed, raising the question of whether proximity to I&M's existing Cook plant operating experience, not site quality, drove the choice. The CANDU option also imports a heavy-water supply chain with no U.S. production source and a full dependency on Canada, a detail missing from the state's framing of the announcement as energy independence. Either way, a 960-MW Xe-100 build is really twelve sequential first-of-a-kind construction projects requiring a specialized HTGR craft workforce that doesn't currently exist in Indiana.
- Watch
- Progress on the AtkinsRéalis/Hoosier Energy CANDU feasibility study and whether either Indiana nuclear proposal reaches a published site decision or final investment decision milestone.
- For the huddle
With Indiana running two separate nuclear site competitions at once (Xe-100 at Breed vs. CANDU reactors elsewhere), do we have a read on which technology and timeline is more likely to actually deliver power we can plan around?
Neither has a confirmed cost, construction date, or in-service date yet, so treat Indiana's next big power source as still in the feasibility stage and build your own power planning on what's confirmed today, not either proposal.
Sources
- Indiana nuclear proposals target retired fossil plant sites · powermag.com
Earlier coverage
- Amazon, AEP, and X-energy Weigh 960 MW Nuclear Plant in Sullivan County
- Sullivan County Siren Outage Exposes Indiana Data Center Power Risk
- Merom Generating Station Gets $27M Federal Subsidy and a 12-Year NIPSCO Data Center Deal
- Hallador Merom: What the DOE Award Actually Is, and the NIPSCO-Hallador Capacity Deal That Isn't
- $65B Industrial Park Proposed in Sullivan County
From the brief, October 24, 2026
- Samsung SDI Takes Full Ownership of the New Carlisle Indiana Battery Plant
- Amazon Funds 12 Nuclear Reactors Near Terre Haute
- AEP and X-energy Formalize Breed Station Plan Amid a Competing CANDU Bid
- GM Confirms Brownstown Battery Plant Closure Alongside $20 Billion Buyback
This story
Related
Manufacturers Energy Grant Program
Free for Sullivan County manufacturers
Sullivan County manufacturers receive free, ongoing energy auditing and cost control that reduces their energy bills and keeps them low, month after month. Every line item checked and validated, every opportunity found comes with a step-by-step guide to capture it.
EDCs: sponsor this program and it carries your organization's name For economic developers →