October 25, 2026 · Martin · LaPorte · Bartholomew
Navy's Crane Indiana Microreactor Deal, Cummins' Rating Reversal, and Wabash National's Idle Goshen Plant
The Crane Indiana microreactor deal brings zero local jobs, and Cummins, KTR, and Wabash National all make news Indiana manufacturers need this week.
The Navy named California startup Radiant Industries as builder of record for a Crane Indiana microreactor project on October 20, a deal that brings the state its first power reactor of any kind and zero manufacturing jobs to go with it. The same week, Wall Street Zen reversed its own eight-day-old downgrade of Columbus-based Cummins, KTR Corporation filed for a $15 million expansion in Michigan City, and Hyundai Translead added a third round of hiring in Illinois while Wabash National's Goshen, Indiana trailer plant sits idle. Here is what each one means for your plant floor this week.
02LaPorte
KTR Corporation Plans $15 Million Expansion in Michigan City
KTR Corporation, the U.S. arm of German coupling maker KTR Kupplungstechnik, is consolidating its North American headquarters and manufacturing into a new 78,000-square-foot facility on 22 acres along CR 400 North in Michigan City. The La Porte County Board of Zoning Appeals approved the special use variance this past Tuesday.
- For the huddle
- Given KTR's wind-coupling exposure to the direct-drive shift, should we be asking Eric Stachowiak or EDCMC whether hydraulic components or couplings are driving the majority of the new 78,000-square-foot buildout before assuming this is a straightforward capacity story?
SourcesMichigan City Manufacturer Planning Expansion (hometownnewsnow.com)
03Statewide
Cummins Gets Whipsawed by Its Own Rating Agency in Eight Days
Wall Street Zen upgraded Columbus-based Cummins from hold back to buy on Sunday, eight days after downgrading the stock from buy to hold on October 17. The reversal landed amid a wave of price-target cuts from Citigroup, Barclays, Truist, JPMorgan and Bank of America, and shares opened Friday at $517.64, below both the 50-day and 200-day moving averages.
04Statewide
Audi's $4.2 Billion Georgia Plant Opens a Tariff-Exemption Window
President Trump announced Saturday at a Perry, Georgia rally that Audi will build its first U.S. plant near Macon, a $4.2 billion commitment to produce 200,000 vehicles a year and roughly 4,500 jobs, with construction starting in 2027 and production in the early 2030s. The announcement reads less like a growth story and more like a tariff-exemption certification.
- For the huddle
- Do any of our existing Tier 1 relationships run through Volkswagen Group's Chattanooga plant, and if so, should we be positioning for a Georgia logistics footprint now, before the Macon supply chain locks in around 2028?
SourcesTrump Announces Audi’s First-Ever U.S. Factory in Georgia as Tariffs Bite (newsday.com)
05Statewide
Hyundai Translead Adds 1,250 Jobs While Wabash National's Goshen Plant Sits Idle
Hyundai Translead announced Thursday it is adding 1,250 jobs on top of the 2,500 it committed in March, bringing its total commitment in Will County, Illinois to 3,750 jobs and $600 million across two new semi-trailer factories near Joliet. Governor J.B. Pritzker's office called it the largest manufacturing job commitment in recent Illinois history, and the state is funding a new training academy at Joliet Junior College that will double the school's welding capacity.
- For the huddle
- If Hyundai Translead is confident enough in trailer demand to add a third shift in Illinois right now, what does that tell us about the realistic timeline for Wabash's Goshen plant to restore jobs, and should we be planning around a 2027 recovery or a longer freight downturn?
Sources3,750 new manufacturing jobs backed by tax credits announced for Hyundai (aol.co.uk)
Questions for your morning huddle
- If the reactor arrives factory-fueled and goes back to Tennessee for refueling, is there any realistic entry point for an Indiana supplier into the TRISO fuel, helium-cooling, or microreactor-container supply chain, or does this stay a pure power-purchase deal with zero local manufacturing upside?
- Given KTR's wind-coupling exposure to the direct-drive shift, should we be asking Eric Stachowiak or EDCMC whether hydraulic components or couplings are driving the majority of the new 78,000-square-foot buildout before assuming this is a straightforward capacity story?
- Do any of our existing Tier 1 relationships run through Volkswagen Group's Chattanooga plant, and if so, should we be positioning for a Georgia logistics footprint now, before the Macon supply chain locks in around 2028?
- If Hyundai Translead is confident enough in trailer demand to add a third shift in Illinois right now, what does that tell us about the realistic timeline for Wabash's Goshen plant to restore jobs, and should we be planning around a 2027 recovery or a longer freight downturn?
This brief
More from Martin County
- Indiana Grid Capacity Tightens as Crane Lands a Microreactor and Kokomo Pitches a 1.5-Gigawatt Data Center
- AES Indiana Rate Increase Rehearing, Duke Energy's New Industrial Sites, and Amazon's $100 Million Greenwood Plant
- Amazon's Greenwood Robotics Plant and the AES Indiana Rate Increase Rehearing: What Indiana Manufacturers Need to Watch
Manufacturers Energy Grant Program
Free for Indiana manufacturers
Manufacturers from qualifying Indiana counties receive free, ongoing energy auditing and cost control that reduces their energy bills and keeps them low, month after month. Every line item checked and validated, every opportunity found comes with a step-by-step guide to capture it.
EDCs: sponsor this program and it carries your organization's name For economic developers →