Duke's 128-Week Transformer Delay Lands Inside Your Project Timeline
Duke Energy Indiana president Stan Pinegar told a Greater Lafayette Commerce panel the company is in "supply chain hell" sourcing equipment, citing a 128-week lead time on large power transformers, a two-and-a-half-year wait on a single piece of infrastructure. CenterPoint and Tipmont raised the same concern. The cost question underneath it: TDSIC lets utilities recover infrastructure spend between rate cases across the whole customer base, and whether data center-driven upgrades get allocated that way rather than to the load that required them is active in current IURC filings. If your expansion depends on a utility-side substation upgrade, that lead time now sits in your critical path, ask your Duke or AES account rep for your interconnection queue position in writing before you commit capex.
Duke's $350,000 Summer Assistance and the Regulatory Subtext
Duke Energy Indiana announced a $350,000 shareholder-funded, not ratepayer-funded, summer bill assistance program for residential customers. The timing matters: Congress is debating the future of LIHEAP, the primary federal affordability mechanism Indiana utilities lean on, and a shareholder-funded gesture builds a visible goodwill record at the IURC while Duke has active proceedings and the commission is being reconstituted. Watch whether other Indiana utilities follow before the next rate case cycle opens.
For your morning huddle
- Q
Do 128-week transformer lead times affect our expansion project?
If your expansion depends on a utility-side substation or transformer upgrade, the 128-week large power transformer lead time Duke cited now sits inside your project's critical path, not your utility's. Ask your Duke or AES account rep for your current interconnection queue position in writing before you commit capex.
From the brief, July 10, 2026
- POET's Shelbyville Expansion and the Unfinished 45Z Credit Math
- The IURC Rebuild Puts AES Rate Exposure on a Knife's Edge
- Workforce Pell Is Live in Indiana, But Only Three Programs Qualify
- Duke's 128-Week Transformer Delay Lands Inside Your Project Timeline
TEG Daily, before your morning huddle
A short Indiana energy and manufacturing scan, delivered before the workday starts.
Related
- PMG Indiana Columbus Closure: 150 Jobs Gone by Dec. 31, Plus GovParts and MelKay Risk for Indiana Plant Leaders
- Canada Tariffs, Rolls-Royce, and Burns Harbor: What Indiana Manufacturers Need to Act On This Week
- Rolls-Royce $1B Indianapolis Finish Line: What Marion County Suppliers and Indiana Manufacturers Need to Track Now
Manufacturers Energy Grant Program
Free for Indiana manufacturers
Manufacturers from qualifying Indiana counties receive a free monthly 35-point audit of their electric bills for cost recovery and savings. Every line item checked and validated, every opportunity found comes with a step-by-step guide to capture it.
EDCs: sponsor this program and it carries your organization's name For economic developers →