Indiana Grid Capacity Tightens as Crane Lands a Microreactor and Kokomo Pitches a 1.5-Gigawatt Data Center

A Crane nuclear microreactor, Kokomo's 1.5-gigawatt data center bid, and a third Burns Harbor furnace delay show how fast Indiana grid capacity is disappearing.

The U.S. Navy selected Radiant Industries to build a nuclear microreactor at Naval Weapons Station Crane in Martin County, and Digital Realty proposed a 1.5-gigawatt data center campus in Kokomo that would draw from the same Duke Energy and NIPSCO generation Indiana manufacturers already compete for. Both decisions landed this week alongside a third delay to Cleveland-Cliffs' Burns Harbor blast furnace reline in Porter County, a new dry ice plant opening in East Chicago, and a vague letter of intent for a 10-megawatt data center project with no disclosed site. For plant managers in Howard, Martin, Lake, and Porter counties, the practical read is the same: Indiana grid capacity is getting claimed fast by very large, non-manufacturing projects, and your interconnection timeline and your steel contract are both affected by it.

01Martin

Radiant's Kaleidos Microreactor Headed to NSWC Crane in Martin County

The Navy picked Radiant Industries to install a 1-megawatt Kaleidos nuclear microreactor at Naval Weapons Station Crane, the first time the Navy has put an advanced reactor on a shore-based installation. The Department of War wants it running by September 2028 to protect Crane's microelectronics and weapons-testing work from grid disruption.

For the huddle
Should our skilled-trades and environmental-consulting capacity be positioning now to bid on NRC licensing and site-prep work at Crane, given the solicitation window is expected to open well before the 2028 deadline?

SourcesUS Navy Picks Radiant Microreactor to Power Indiana Base (thedefensepost.com)

Read the story →

02Howard

Digital Realty's 1.5-Gigawatt Data Center Pitch Tests Indiana Grid Capacity in Kokomo

Digital Realty is proposing a three-building, 1-gigawatt data center campus on 476 acres in Kokomo, an investment Mayor Tyler Moore's office and other reporting have put anywhere from $1 billion to $3 billion, with completion targeted for 2033. The completed campus would draw about 1.5 gigawatts from Duke Energy, and the Kokomo Common Council already rezoned the site for data centers in September without adding stricter noise or utility rules, a decision that stands out because at least 28 Indiana counties and 10 cities, including Indianapolis through 2027, have passed data center moratoriums.

For the huddle
If this campus pulls skilled trades labor and drives up wages across Howard County the way comparable hyperscale builds have elsewhere, what's our retention plan for the next 2-3 years of construction activity?

SourcesDigital Realty proposes 1GW data center campus in Indiana (datacenters.economictimes.indiatimes.com)

Read the story →

03Lake

Sutton-Garten Opens a 17,000-Square-Foot Dry Ice Plant in East Chicago

Indianapolis-based Sutton-Garten is holding a Nov. 11 grand opening for its new dry ice production plant in East Chicago, a 17,000-square-foot building that took $2 million in renovations and got knocked off schedule by the Aug.

For the huddle
Before we lean on regional suppliers like Sutton-Garten for dry ice or industrial cleaning services, have we confirmed they've locked in long-term CO2 supply contracts ahead of a potential 2026 feedstock crunch?

SourcesSutton-Garten Co. plans East Chicago opening (nwindianabusiness.com)

Read the story →

04Porter

Cleveland-Cliffs Delays Burns Harbor Blast Furnace Reline a Third Time

Cleveland-Cliffs has pushed back the lining replacement on blast furnace C at its Burns Harbor plant in Porter County from mid-2027 to April 2028, the third delay since the work was first scheduled for 2025. The company disclosed the delay on its third-quarter earnings call, where it also reported steel shipments up 3% year over year to 4.2 million tons, even though shipments for the first nine months of the year are down 1.4%.

For the huddle
Are our steel supply contracts with Cleveland-Cliffs still fixed-price, or have we already been shifted onto the index-linked, take-or-pay terms behind the $850 million repricing benefit they disclosed this quarter?

SourcesCleveland-Cliffs has carried out refurbishment work on a blast furnace at its plant in Indiana (gmk.center)

Read the story →

05Statewide

Brightray's 10-Megawatt Data Center Letter of Intent Names No Indiana Site

Brightray Veridian, a subsidiary of Nasdaq-listed BUUU Group, signed a non-binding letter of intent on Oct. 6 for a 10-megawatt prefabricated AI data center somewhere in Indiana, its first proposed U.S. project.

For the huddle
Before treating this LOI as a signal of real Indiana construction activity, should we wait to see if the Nov. 15 purchase-order deadline is actually met, given BUUU's recent stock split and the all-stock structure behind its Brightray acquisition?

SourcesBrightray Signs LOI for Planned 10MW Prefab Data Center in Indiana (news.constructconnect.com)

Read the story →

Questions for your morning huddle

  1. Should our skilled-trades and environmental-consulting capacity be positioning now to bid on NRC licensing and site-prep work at Crane, given the solicitation window is expected to open well before the 2028 deadline?
  2. If this campus pulls skilled trades labor and drives up wages across Howard County the way comparable hyperscale builds have elsewhere, what's our retention plan for the next 2-3 years of construction activity?
  3. Before we lean on regional suppliers like Sutton-Garten for dry ice or industrial cleaning services, have we confirmed they've locked in long-term CO2 supply contracts ahead of a potential 2026 feedstock crunch?
  4. Are our steel supply contracts with Cleveland-Cliffs still fixed-price, or have we already been shifted onto the index-linked, take-or-pay terms behind the $850 million repricing benefit they disclosed this quarter?
  5. Before treating this LOI as a signal of real Indiana construction activity, should we wait to see if the Nov. 15 purchase-order deadline is actually met, given BUUU's recent stock split and the all-stock structure behind its Brightray acquisition?

This brief

More from Martin County

Manufacturers Energy Grant Program

Free for Indiana manufacturers

Manufacturers from qualifying Indiana counties receive free, ongoing energy auditing and cost control that reduces their energy bills and keeps them low, month after month. Every line item checked and validated, every opportunity found comes with a step-by-step guide to capture it.

EDCs: sponsor this program and it carries your organization's name For economic developers →